New design completed for Port Kaituma Stelling after fissures detected – Contractor
See below the statement issued by International Import and Supplies – the contractor working on the Port Kaituma Stelling:
International Import and Supplies addresses recent misinformation circulating about the Port Kaituma Stelling construction project, seeking to protect the reputation of the company and its proprietor.
Contract Award and Scope
International Import and Supplies was awarded the contract to construct the Port Kaituma Stelling on December 30, 2022 through a process of Public Tender. The Contractor’s scope was limited to the construction of the physical structure. The design and project supervision were undertaken separately by a local Consultancy firm.
Material Procurement and Construction Progress
Procurement of materials was executed in accordance with the Project Specifications and Bill of Quantities; with critical elements sourced from pre-approved suppliers in Europe and China. As of February 18, 2024, the project was on schedule and approximately 90% completed. During the final stages of casting pile caps, fissures were observed within the backfilled area, prompting an immediate cessation of work and notification to the Consultant and Ministry.
Investigation and Findings
Initial investigations indicated that the tie rod strength specified in the design was inadequate. An independent third-party firm was subsequently engaged to review the initial design, revealing additional deficiencies in the design, particularly in the affected zone of the structure. The Ministry has subsequently retained this firm to conduct a new geotechnical survey and prepare a revised design.
New Design Implementation
A new independent design has been completed which has addressed the deficiencies identified in the initial design which includes the implementation of longer and thicker piles and tie rods. These items have already been procured and preparations are underway to resume work on the project.
Commitment to Quality and Transparency
International Import and Supplies wishes to emphasize that there is an intentional attempt to attack the reputation of the company and its proprietor. The company remains committed to delivering quality projects and will continue to operate with a high level of transparency. We are committed partners of development with the Government of Guyana and will ensure that value for money is provided and that a quality Stelling will be delivered to benefit the citizens, as intended. We maintain again that the initial failure of the revetment was assessed to be due to a design flaw beyond the control of the company.
Closing Statement from the Company
Our integrity remains intact, with a history of completing 100% of our contracts, and addressing any defects during and after the liability period. We apologize for any inconvenience caused and assure the public of our dedication to excellence.
Comments